Thursday, July 30, 2009

DAY 3 30 july

Wednesday, July 29, 2009






day 2, 29 july 2009


view of the platform ceiling frame from stairways





(below)stairsways hacked










wall almost fully done metal bar placed on top to secure the wall

(right) cement in









hole dug out to prepare the water meter to be shifted out side of the extension wall.


Tuesday, July 28, 2009

work start DAY 1 28 july 2009
workers came early
cement and bricks and sand came






platform ceiling frame already fully set up by evening


















hollow blocks be unloaded.... "foundation metal bar " which will form
the column bars

by late afternoon wall of the extension is half done

working on the column



















owner mr J came by discussing leaking issues at around 5pm