Thursday, August 13, 2009

Day 18 13 August 2009

more painting work past 2 days
front gate paint job completed
3 coats of paint

2nd and 3rd floor painting is ongoing














2nd floor toilet bi-fold door install















partition at 1st floor separating the toilet/kitchen area

tomorrow the aluminium sliding door will be installed










Owner ask his own workers to redo toilet floor at 3rd floor, started work today